Projects & phases

Follow a development across phases, funding records and reported results. Each observation keeps its own date and evidence status.

Original research snapshot: November 8, 2026. Later findings retain their own source dates.

One place can appear in several records.

10 developments and one neighborhood planning area are listed here. They are a selected research set, not a complete Phoenix inventory. Phase, inventory, designation and completion figures are not additive.

Two Phoenix housing projects: What the City certified

Phoenix certified that Phoenix Scholar House, a 56-home development, met the terms of its City HOME development loan agreement as of October 26, 2026. The certificate was recorded November 6, 2026. City certificate of completion, p. 1 (20260641371).

The City separately certified contractual completion for La Esperanza Terrace as of January 12, 2026. The certificate covers 96 homes and was recorded January 29, 2026. City certificate of completion, p. 1 (20260052973).

These certificates document completion under the respective City agreements. They do not establish final payments, HUD financial closeout, current occupancy or apartment availability.

Goodyear plans home repairs and legal help for renters

Goodyear’s 2026–27 action plan lists $323,561 for repairs to owner-occupied homes, $62,268 for legal services for renters facing unlawful eviction, and $96,457 for administration. Those three lines total $482,286. The plan covers July 1, 2026 through June 30, 2027. These figures are planned uses; they do not show how much was paid, whether services have started, or how many households got help. Read the City’s project breakdown.

Chart note: The chart shows annual HUD allocations to named direct CDBG grantees, not spending, subawards, or households served. Regional charts cover selected recipients only. A municipality can participate in a county-administered program without appearing as a separate direct grantee for every year.

Open the allocation charts and source tables

Goodyear’s direct HUD allocations

HUD regular CDBG formula allocations · federal FY2020–26 · nominal dollars

Goodyear’s regular Community Development Block Grant awards, federal fiscal years 2020–2026.There is no direct HUD row for 2020. Six annual allocations run from $429,038 in 2021 to $482,286 in 2026, with a low of $397,718 in 2023. The exact-value table follows.$0k$150k$300k$450k$600k’20’21’22’23’24’25’26—$482,286
Goodyear’s FY2026 HUD allocation was $482,286, up $67,164 (16.2%) from FY2025. HUD’s FY2020 workbook had no separate Goodyear row. This chart does not track County-administered projects or City spending.
Exact HUD formula allocations in nominal dollars
Federal FYGoodyear
2020—
2021$429,038
2022$426,876
2023$397,718
2024$426,647
2025$415,122
2026$482,286

— means no separate allocation row in the checked HUD workbook, not a $0 award. Year links download HUD’s annual spreadsheets.

Maricopa County area: four selected direct grantees

HUD regular CDBG formula allocations · federal FY2020–26 · nominal dollars

  • Phoenix
  • Mesa
  • Maricopa County
  • Glendale
Direct HUD CDBG allocations for Phoenix, Mesa, Maricopa County and Glendale, federal fiscal years 2020–2026.On a shared zero-based scale, Phoenix is the largest of these four direct grantees and declines from $16,694,589 to $14,096,474. The three smaller series are listed in the exact-value table.$0m$5m$10m$15m$20m’20’21’22’23’24’25’26
Phoenix’s FY2026 allocation was $14.10 million, down from $16.69 million in FY2020. This is a selected comparison, not a region total. Maricopa County’s line covers the County’s award, not the sum of awards across its cities.
Exact HUD formula allocations in nominal dollars
Federal FYPhoenixMesaMaricopa CountyGlendale
2020$16,694,589$4,066,246$3,206,671$2,477,347
2021$16,806,480$4,286,734$2,890,618$2,459,350
2022$15,680,741$4,185,727$2,836,377$2,368,223
2023$15,425,793$4,050,391$3,020,680$2,354,682
2024$14,461,954$3,868,757$2,939,131$2,351,551
2025$14,389,727$3,675,410$2,940,912$2,376,397
2026$14,096,474$3,524,255$2,932,133$2,319,746

— means no separate allocation row in the checked HUD workbook, not a $0 award. Year links download HUD’s annual spreadsheets.

Pima County area: three selected direct grantees

HUD regular CDBG formula allocations · federal FY2020–26 · nominal dollars

  • Tucson
  • Pima County
  • Marana
Direct HUD CDBG allocations for Tucson, Pima County and Marana, federal fiscal years 2020–2026.Tucson declines from $5,602,779 to $4,962,047 and Pima County declines from $2,971,606 to $2,468,397. Marana has no separate row for 2020–2022; its line starts at $208,691 in 2023. Exact values follow.$0m$1.5m$3m$4.5m$6m’20’21’22’23’24’25’26
Tucson, Pima County and Marana had separate FY2026 direct allocations. Marana’s series begins at its first separate row in the checked federal files, FY2023. Earlier years are gaps, not zeros. The County may fund individual projects in its service area; its allocation is not a total that includes all municipal grants.
Exact HUD formula allocations in nominal dollars
Federal FYTucsonPima CountyMarana
2020$5,602,779$2,971,606—
2021$5,732,384$3,000,218—
2022$5,406,671$2,746,895—
2023$5,268,216$2,665,598$208,691
2024$5,068,664$2,567,968$210,183
2025$5,108,670$2,593,824$207,209
2026$4,962,047$2,468,397$223,434

— means no separate allocation row in the checked HUD workbook, not a $0 award. Year links download HUD’s annual spreadsheets.

Sources and method

HAP matched Arizona grantee names and HUD grantee keys to the regular CDBG column in the original annual formula allocation workbooks. The checked set contains 19 named places or grantees, 133 place/year checks and 101 direct HUD allocations. It is not an inventory of all CDBG-supported activity. Allocations are not adjusted for inflation, and do not include separately reported CDBG-CV or disaster funds.

Download the 133 checked source rows (CSV). Each positive row has a source workbook, sheet, cell and exact amount. A blank amount represents no separate row; never replace it with zero.

HUD’s Community Development Block Grant program overview · City of Goodyear’s CDBG records

Laveen Commons: Up to $40 million in preliminary bond financing

On November 19, the Phoenix Industrial Development Authority gave preliminary approval to up to $40 million in bond financing for Laveen Commons at 7260 South 59th Avenue. This is a separate project from Laveen Park Place. The approval does not show that bonds were issued, financing closed, or homes were delivered.

Board results, page 2, item 6 (PDF)

11 entries

Prints all matching entries with connected evidence expanded. Save a PDF from the print dialog.

Direct link

25th @ Bell

Place
16801 N. 25th Street · Phoenix
Stage & date
Reported completed · draft FY2025–26 CAPER
Homes
53 reported apartments
Funding record
Separate City and State HOME activities; funding fields are not verified cash payments.

Assisted-unit designations can overlap. Draft completion reporting does not establish current occupancy or vacancies.

Read the published context →
Dates, funding & sources

One development connects City and State HOME activities, dated ARPA statements and a draft completion report.

Keep in mind

The two activities do not create 106 apartments. HOME and ARPA unit overlap, current ownership, actual payments and current occupancy remain unverified.

Connected evidence (11)
Related published questions
Direct link

Pueblo Apartments

Place
Phoenix
Stage & date
Reported completed · draft FY2025–26 CAPER
Homes
161 reported apartments
Funding record
A complete financing history and comparable spending total are not established here.

This is one of five reported projects, not a separate citywide housing total or a current availability listing.

Read the published context →
Dates, funding & sources

One of five developments in the published draft CAPER completion subtotal.

Keep in mind

The grouped performance-report finding is not a separate project audit, current occupancy record or verified financing stack.

Connected evidence (1)

The publication has no separate project-specific question entry for this development or area. The broader Phoenix questions remain open.

Direct link

Garfield II

Place
Phoenix
Stage & date
Reported completed · draft FY2025–26 CAPER
Homes
60 reported apartments
Funding record
A complete financing history and comparable spending total are not established here.

Match the project's identity before combining it with another Garfield phase.

Read the published context →
Dates, funding & sources

A separately named development in the published draft CAPER completion subtotal.

Keep in mind

The reviewed publication does not establish a full project or financing history. Do not combine this count with another Garfield phase without matching its identity.

Connected evidence (1)

The publication has no separate project-specific question entry for this development or area. The broader Phoenix questions remain open.

Direct link

Residences at Falcon Park

Place
Phoenix
Stage & date
Reported completed · draft FY2025–26 CAPER
Homes
192 reported apartments
Funding record
A comparable project-spending total is not established in the reviewed finding.

Draft reported completion does not establish current occupancy or available apartments.

Read the published context →
Dates, funding & sources

One of five developments in the published draft CAPER completion subtotal.

Keep in mind

This is a draft reported-completion observation, not verified current occupancy or a current availability listing.

Connected evidence (1)

The publication has no separate project-specific question entry for this development or area. The broader Phoenix questions remain open.

Direct link

Harmony at the Park

Place
Phoenix · three phases
Stage & date
Existing inventory · May 2026 directory; Phase III also in draft FY2025–26 CAPER
Homes
120 + 115 + 90 apartments; 325 across all phases
Funding record
A comparable spending total across the three phases is not established here.

Phase III's 90 apartments appear in both records. Do not add the draft completion count to the 325-home inventory.

Read the published context →
Dates, funding & sources

Phase III appears in the draft completion report; the directory describes inventory across all three phases.

Keep in mind

Phase III's 90 apartments appear in both observations. The 325 inventory total is not additional FY2025–26 production; do not add these figures.

Connected evidence (2)

The publication has no separate project-specific question entry for this development or area. The broader Phoenix questions remain open.

Direct link

The Moreland

Place
Phoenix · former Deck Park Vista site
Stage & date
Planned phases · June 17, 2026 Council scope report
Homes
132 Phase I + 105 Phase II planned apartments
Funding record
Phase I: $43.1m reported closing, December 2025. Phase II: up to $10m authorized, June 17, 2026.

237 is planned scope, not completed Phase I housing. Closing and authorization amounts are not City spending; Phase II's fund split and execution remain unverified.

Read the published context →
Dates, funding & sources

Two planned phases have different financing records and must remain separately identified.

  • Planned scope · June 17, 2026 Council report

    Phase I: 132 apartments. Phase II: 105. Combined planned scope: 237. At the June 17, 2026 Council action, the staff report described Phase I as under construction and forecast completion in February 2028.

    Read the record · PHX-WEB-007
  • Phase I · reported financing closing

    $43.1 million reportedly closed in December 2025 after approval of up to $50 million. Neither is a City spending total.

    Read the record · PHX-WEB-009
  • Phase II · June 17, 2026 authorization

    Up to $10 million from mixed funding sources and up to 54 project-based vouchers; execution and fund split remain unverified.

    Read the record · PHX-WEB-010
Keep in mind

237 is the planned two-phase scope, not completed Phase I apartments. Approval, closing, assistance and payment figures are not interchangeable or additive. The February 2028 forecast reflects the June 2026 report. Current construction status and actual completion remain unverified.

Connected evidence (3)
Related published questions
Direct link

Girasol

Place
Phoenix · former Sidney P. Osborn site
Stage & date
Dated construction progress · October 26, 2026
Homes
364 planned gross apartments; 289 affordable + 75 market-rate
Funding record
A comparable project-spending total is not established in this summary.

Gross redevelopment scope is not net new housing. Construction percentages and move-in forecasts are not occupied homes.

Read the published context →
Dates, funding & sources

Three redevelopment subphases on the former Sidney P. Osborn site, with dated construction forecasts.

  • Planned gross scope · October 26, 2026

    364 apartments: 289 affordable and 75 market-rate.

    Read the record · PHX-WEB-020
  • Construction progress · October 26, 2026

    Phase I: 82% complete. Phase II: 79% complete. Early-2027 move-ins were forecast; Phase III construction was forecast for Q1 2027 and move-ins for 2028.

    Read the record · PHX-WEB-020
Keep in mind

These are Girasol subphases, not Harmony phases. Gross redevelopment units are not net additions; construction percentages and forecasts are not occupied apartments.

Connected evidence (1)

The publication has no separate project-specific question entry for this development or area. The broader Phoenix questions remain open.

Direct link

Marcos de Niza–Grant Park

Place
Phoenix · neighborhood planning area
Stage & date
HUD planning award announced · September 10, 2024
Homes
No apartment-delivery count established by this award
Funding record
$500,000 announced for planning and transformation-plan work.

A planning award does not establish construction funding, grant spending or completed homes.

Read the published context →
Dates, funding & sources

A neighborhood planning award, kept separate from the development entries.

Keep in mind

This is not a construction implementation award, evidence of grant spending or an apartment-delivery count.

Connected evidence (1)

The publication has no separate project-specific question entry for this development or area. The broader Phoenix questions remain open.

DevelopmentDirect link

Phoenix Manor

Phoenix, Maricopa County · senior apartments at Phoenix Manor

  • Investor-reported renovation and affordable conversion

    R4 Capital describes renovating and converting 450 existing Phoenix Manor apartments from market-rate to affordable senior housing. Count the 450 as preservation of existing apartments.

    Read the record · PHX-WEB-028
Keep in mind

Occupancy, household outcomes and the timing and terms of affordability restrictions require separate evidence. The 450 apartments are existing stock.

Connected evidence (1)
Related published questions
Read the published context
DevelopmentDirect link

La Victoria Commons

Tempe, Maricopa County · La Victoria Commons

  • Proposed ground leases

    Tempe’s April 2024 Council agenda identified two 52-apartment financing portions, one using 4% and one using 9% Low-Income Housing Tax Credits. Together the proposal describes 104 apartments. The 19 for-sale townhomes are a separate component.

    Read the record · PHX-WEB-029
  • Dated opening reports

    Tempe reported on March 2, 2026 that the 104 affordable rental apartments had opened and were leasing. Project partner MolinaCares corroborates the February 26 grand opening.

    Read the record · PHX-WEB-029
Keep in mind

The 2026–27 Tempe housing agency plan summary lists 109 rental units. The final count has not been independently reconciled. Current rental vacancies and completion or sales of the 19 townhomes are not independently confirmed. The 2024 agenda identifies proposed ground leases, not executed leases or a financing close. Its meeting date and the 2026 opening reports do not establish an active funding period or disbursement.

Connected evidence (1)
Related published questions
Read the published context
DevelopmentDirect link

Salvation Army family shelter expansion

Phoenix District 8, Maricopa County · Salvation Army family shelter expansion

  • Adopted City funding authority and site dedication

    Phoenix replaced the original $6 million CDBG and CDBG-CV commitment with up to $6 million in HOME-ARP in 2023. Council added up to $2 million in 2025, bringing the HOME-ARP authority to $8 million. The City announced the site dedication on May 12, 2026.

    Read the record · PHX-WEB-030
Keep in mind

The initial CDBG commitment was replaced and cannot be added again. Funding authority does not establish cash paid. The ceremony marked the site for future construction. Opening, expenditures and people served by the expansion remain unverified. The December 3, 2025 Council report describes a $10 million total project cost and a loan. The May 12, 2026 City announcement describes an estimated $8 million project and a grant. The reviewed sources leave the differences unexplained. An executed agreement, any amendments and a reconciled budget are needed to establish the terms and cost.

Connected evidence (1)
Related published questions
Read the published context